Project Background

Between the 31 October and 11 November 2022, Melton City Council shared a proposed landscape plan with local residents to upgrade Splendour Circuit Reserve.

The project is now complete with the installation of additional play equipment, improvements to associated amenities and the inclusion of additional understorey planting and trees for shade.

Have Your Say

Thank you to everyone who provided feedback. We assessed the feedback we received from the community and are revised the landscape concept plan.

Timeline

  • Timeline item 1 - complete

    Community Feedback

    Survey opens 31 October and closes 11 November 2022

    Gathering feedback from the local community on what is important to them to help direct how we prioritise the works.

  • Timeline item 2 - complete

    Evaluation

    Mid to late November 2022

    Taking the feedback and examining it.

  • Timeline item 3 - complete

    Finalise Design & Procurement

    Late November – mid December 2022

    Finalise a design that reflects the feedback and fits within the budget, then procure the proposed equipment and/or infrastructure.

  • Timeline item 4 - complete

    Lead Times

    January – April 2023*

    Awaiting the manufacturing and shipping of items.

  • Timeline item 5 - complete

    Construction/Installation

    June - August 2023*

    Construction and/or installation of the proposed upgrade.


    * Denotes an estimate timeframe only, based upon experience with recent projects.