Project Background
The roundabout at Station Road and Brooklyn Road is currently one of busiest intersections in South Melton. There are traffic delays at the roundabout and there are safety concerns for pedestrians and cyclists.
The roundabout will be upgraded to a signalised intersection to ease the congestion at the roundabout, especially when the signals at the level crossing are down. The upgrade will improve the flow of traffic along Brooklyn Road during closure of the level crossing.
The project will include:
- An expansion and realignment of the road
- Underground services relocations (electricity, water, gas, and communications)
- New Traffic signals
- New Public lighting
- Landscaping
The project is valued at $3.5M and construction is expected to begin in the first half of 2023 and be completed by early 2024.
This webpage will be updated as works progress to keep residents informed. To be notified of updates, create an account and select follow at the top of the page.
Swipe to see proposed changes
Have your say
Thank you to everyone who provided feedback. We read all the feedback and you can view the consultation summary in the document library below.
Document library
Frequently asked questions
During works we will minimise disruptions as much as possible and expect that intermittent lane closures will be required.
The majority of the work will occur during work hours, however some night works will occur to avoid having to close road is multiple directions. A curfew will be imposed on the noisiest machinery to avoid disruptions to sleep.
Lane closures will be communicated ahead of time through electronic sign boards to help you plan ahead.
We will work with Public Transport Victoria (PTV) to minimise disruptions to bus services. PTV will let passengers know of any changes to service.Access to the shopping centre and the fuel station will always be maintained.
The construction work is expected to be completed in 6 to 12 months